Parts of Arlozorov Street will be closed to traffic overnight from November 29 to December 3 while crews lay Purple Line light rail tracks. November 29 is also the start date for two long city projects: a roughly 10-month overhaul of Milano Square and the Jaffa Gate project, which is expected to take about 14 months. Mei Avivim will work overnight on Dizengoff Street, and new traffic arrangements are already in effect at several junctions along the light rail route.
Light rail
- Arlozorov track laying (Purple Line): November 29-December 3, 10 p.m.-5 a.m. Arlozorov will be closed to vehicles between Sokolov and Ben Yehuda and between Rabbi Moshe Ben Ezra and Shlomo HaMelech. Work also covers the Arlozorov-Sokolov junction, which will close to vehicles on December 1. Bus stops and routes will change. Information is available from the Kol Kav hotline at *4515.
- HaAliya-Levinsky junction (Purple Line): Starting November 27, for about two months, traffic lanes on HaAliya near the junction will be shifted west and the northern crosswalk will be moved south.
- Arlozorov-HaRav Levi Yitzhak junction (Purple Line): The junction is back in use under a new layout. Drivers coming from the east can turn right from Arlozorov onto HaRav Levi Yitzhak, which becomes a one-way street.
- Arlozorov, Carlebach and Rabin stations (Green Line): Starting December 1, for about a month, crews will pour station walls on Ibn Gabirol Street Sunday through Thursday from 7 p.m. to 11:30 p.m. The work covers the stretches between Arlozorov and Jabotinsky, between Laskov and Kaplan, and between Zeitlin and Bloch. It will stay inside the work sites and will not affect traffic.
- Ben Zvi Road-Gittit junction (Green Line): Work at the junction has been extended by about two months. The western crosswalk on Ben Zvi has been removed and replaced by a new crosswalk on the junction’s east side.
City projects
- Milano Square: Starting November 29, for about 10 months, Sunday through Thursday, 7 a.m.-7 p.m. Ahuzot Hahof will upgrade drainage and lighting, pave a bike path and plant trees. The work will be done in stages, with the first two taking about three months. Traffic will flow as usual.
- Jaffa Gate project: From November 29 through January 2028, carried out by the Atarim company. Work begins at Ruslan Square and will then move into the park and the building at 8 Nahum Goldmann Street. Plans include upgraded walking and bike paths, playground equipment, landscaping, renovated paths down to the beach and a renovated western facade for the building. Traffic arrangements near Ruslan Square will change, but pedestrians and vehicles will still be able to get through to Jaffa Port.
- HaRakevet-La Guardia junction: The city is starting work to upgrade this junction at the southern entrance to Tel Aviv, continuing the Kirya Boulevard project. As part of the work, which Ahuzot Hahof is carrying out, Banda and Rosh Pina streets will no longer connect to the junction.
- Yaakov Mozer Street: Starting December 13, for about two months, Sunday through Thursday, 9 a.m.-5 p.m. The parking area next to Nos. 3 and 5 will be turned into a pedestrian space with fruit trees, plants, seating, bike racks and a community library. The curbs will be painted red and white on December 8, and parking will be banned from December 13.
- Ibn Gabirol, Props to Marc Chagall: A new access road on Ibn Gabirol between Props and Marc Chagall, built to prepare for the Sde Dov neighborhood, was scheduled to open to traffic on November 26.
Water, sewage and power
- Dizengoff 276-296: Starting November 29, for about two weeks, Sunday through Thursday, 10 p.m.-5 a.m., Mei Avivim will dig test pits to locate underground utilities. The work will move section by section, with one lane closed. Bus routes will change. Information is available at *8787.
- Nachmani Street: Starting November 29, for about two weeks, Sunday through Thursday, 9 a.m.-5 p.m. During work hours, the street will be closed to vehicles between Yehuda Halevi and Rothschild Boulevard, and parking will be banned.
- 186 Ben Yehuda: Starting November 29, for about a week, Sunday through Thursday, 10 p.m.-5 a.m. The sidewalk and the parking bay will be closed.
- Sokolov-Jabotinsky junction: November 29, 9 a.m.-5 p.m. The western sidewalk will be closed and a traffic lane will be narrowed.
- 20-24 Bernfeld: Starting November 29, for about four days, 7 p.m.-midnight. The street will be closed to traffic between Baker Zeev and Reifman.
- 3 Yonatan Ratosh: Work that began on November 23 will last about a week, Sunday through Thursday, 9 a.m.-5 p.m. The street is closed to vehicles between Nahum Goldmann and David Raziel, but residents can still get in and out.
- 33 Gush Etzion: November 30-December 3, 10 p.m.-5 a.m.
- 19 HaIrus: Starting December 3, for about three days, 9 a.m.-5 p.m. The path next to the building will be closed.
- 5 Lipsky: Starting December 6, for about four nights, 8 p.m.-5 a.m. The street will be closed to vehicles between Kahanshtam and Moshe Sharett, but residents can still get in and out.
- 13 Lapidot: December 9-10, 9 a.m.-5 p.m. The street will be closed between Moshia and Vatik, with no entry to Lapidot from Moshia.
- 18 Rabbi Meir: Starting December 13, for about three days, 9 a.m.-3 p.m. There will be intermittent closures on Rabbi Meir from Beit Yosef and on Nahliel from Elyashiv.
Other work
- David Shimoni Street: Starting December 2, for about two weeks, Sunday through Thursday, 9 a.m.-5 p.m., crews will lay communications lines. The sidewalk and a traffic lane will be closed, and parking will be banned from December 2.
- 10 Soutine: December 8, 9 a.m.-7 p.m. A crane will be put up at a construction site. The street will be closed to vehicles between Bezalel and David Bloch, and residents will be able to get in and out with help from traffic inspectors.
More information is available on the municipality website.